+* 2014 June 10<br>Rough-in inspections for plumbing, electrical, HVAC, and
+ so forth all completed... on to insulation!
+* 2014.May 8<br>Exterior doors and windows in, roofing begun,
+ duct work underway.
+* 2014.April 26<br>Concrete slabs for basement and garage floor poured.