+* 2014 June 10<br>Rough-in inspections for plumbing, electrical, HVAC, and
+ so forth all completed... on to insulation!
+* 2014.May 8<br>Exterior doors and windows in, roofing begun,
+ duct work underway.
+* 2014.April 26<br>Concrete slabs for basement and garage floor poured.
+* 2014 April 9<br>Roof trusses installed.
+* 2014 March 25<br>Framing started.
+* 2014 March 14<br>Concrete poured for the foundation / basement walls.
+* 2014 March 3<br>Concrete poured for the foundation footers.
+* 2014 February 26<br>Ground broken! Excavation underway...
+* 2014 February 19<br>Building permits issued!
+* 2014 February 7<br>While visiting the site for other reasons, Bdale observed
+ that [Mountain View Electric](www.mvea.coop) has installed a new
+ transformer, riser, and meter base on the last electric pole on our
+ property.
+* 2014 January 22<br>After some iteration between the architect and engineers,
+ we now have a complete working plan set with engineering stamps on
+ the way to Regional for issuance of building permits.