X-Git-Url: https://git.gag.com/?p=web%2Fgag.com;a=blobdiff_plain;f=blackforestfire.mdwn;h=d3d5d7bf5ce0a2a007552ac24f1acd7c933a9a30;hp=6e6567947c314049e645c9f10562f7424f796bf8;hb=f09979cecb37a445ba153773a6a7e5090e8052e9;hpb=3b946534743f0f1c8f7ac34e52069ea110b8d9a6 diff --git a/blackforestfire.mdwn b/blackforestfire.mdwn index 6e65679..d3d5d7b 100644 --- a/blackforestfire.mdwn +++ b/blackforestfire.mdwn @@ -53,6 +53,19 @@ were directly fighting the fire on and around our property: ### Journal ### +* 2014 October 3
Finished cleaning up the apartment and associated garages, + and turned in those keys. +* 2014 September 27
Began to move out of the apartment and in to our new + house! We're home! +* 2014 September 25
Our builder passed his final inspection with regional + building! A list of final (mostly cosmetic) details to finish up, + then we can move in. +* 2014 July 31
Hardwood floors are in, tile floors are in process, finish + electrical has started, trim material in the process of being stained. +* 2014 June 10
Rough-in inspections for plumbing, electrical, HVAC, and + so forth all completed... on to insulation! +* 2014.May 8
Exterior doors and windows in, roofing begun, + duct work underway. * 2014.April 26
Concrete slabs for basement and garage floor poured. * 2014 April 9
Roof trusses installed. * 2014 March 25
Framing started.