X-Git-Url: https://git.gag.com/?p=web%2Fgag.com;a=blobdiff_plain;f=blackforestfire.mdwn;h=d3d5d7bf5ce0a2a007552ac24f1acd7c933a9a30;hp=5c5d35ea6ea6c039d0223bb1861974366c7ba430;hb=b870926c1764caf6a43bd17ac266cfbc597ccf73;hpb=d6001643596d65ae7bdd8caf7bac563858373755 diff --git a/blackforestfire.mdwn b/blackforestfire.mdwn index 5c5d35e..d3d5d7b 100644 --- a/blackforestfire.mdwn +++ b/blackforestfire.mdwn @@ -14,6 +14,11 @@ survived. So we quickly decided to re-build on the same property, and hope the new house will be ready by late summer 2014. In the meantime, we're living in an apartment in nearby Colorado Springs. +If you want to hear more about our experience, feel free to view the video +of Bdale's +[talk at Linux Conf Australia](https://www.youtube.com/watch?v=lJcnllq3VYY) +about the fire and some of the lessons we learned. + ###Helping### For those of you who have asked how you can help us restore and rebuild, @@ -48,6 +53,20 @@ were directly fighting the fire on and around our property: ### Journal ### +* 2014 October 3
Finished cleaning up the apartment and associated garages, + and turned in those keys. +* 2014 September 27
Began to move out of the apartment and in to our new + house! We're home! +* 2014 September 25
Our builder passed his final inspection with regional + building! A list of final (mostly cosmetic) details to finish up, + then we can move in. +* 2014 July 31
Hardwood floors are in, tile floors are in process, finish + electrical has started, trim material in the process of being stained. +* 2014 June 10
Rough-in inspections for plumbing, electrical, HVAC, and + so forth all completed... on to insulation! +* 2014.May 8
Exterior doors and windows in, roofing begun, + duct work underway. +* 2014.April 26
Concrete slabs for basement and garage floor poured. * 2014 April 9
Roof trusses installed. * 2014 March 25
Framing started. * 2014 March 14
Concrete poured for the foundation / basement walls.