X-Git-Url: https://git.gag.com/?p=web%2Fgag.com;a=blobdiff_plain;f=blackforestfire.mdwn;h=bb48a659d8e4a92b81f050c7e61145c091b27327;hp=e34ca844ac459443d0f1c9babc2bd05df15361a7;hb=9faadf2eca629ce7d6b292109100111be20de113;hpb=de891d1500efba5b0ad14994ca93cf3e6c11eb6a diff --git a/blackforestfire.mdwn b/blackforestfire.mdwn index e34ca84..bb48a65 100644 --- a/blackforestfire.mdwn +++ b/blackforestfire.mdwn @@ -45,6 +45,16 @@ were directly fighting the fire on and around our property: fire. ### Journal ### +* 2014 March 3
Concrete poured for the foundation footers. +* 2014 February 26
Ground broken! Excavation underway... +* 2014 February 19
Building permits issued! +* 2014 February 7
While visiting the site for other reasons, Bdale observed + that [Mountain View Electric](www.mvea.coop) has installed a new + transformer, riser, and meter base on the last electric pole on our + property. +* 2014 January 22
After some iteration between the architect and engineers, + we now have a complete working plan set with engineering stamps on + the way to Regional for issuance of building permits. * 2013 December 16
Got our "last" set of questions answered by our contractor, and signed the contract for constuction of our new house. * 2013 December 10
Met with contractor to review cost estimates for our