### Journal ###
+
+* 2014 March 25
Framing started.
+* 2014 March 14
Concrete poured for the foundation / basement walls.
+* 2014 March 3
Concrete poured for the foundation footers.
+* 2014 February 26
Ground broken! Excavation underway...
+* 2014 February 19
Building permits issued!
+* 2014 February 7
While visiting the site for other reasons, Bdale observed
+ that [Mountain View Electric](www.mvea.coop) has installed a new
+ transformer, riser, and meter base on the last electric pole on our
+ property.
+* 2014 January 22
After some iteration between the architect and engineers,
+ we now have a complete working plan set with engineering stamps on
+ the way to Regional for issuance of building permits.
* 2013 December 16
Got our "last" set of questions answered by our
contractor, and signed the contract for constuction of our new house.
* 2013 December 10
Met with contractor to review cost estimates for our