X-Git-Url: https://git.gag.com/?p=web%2Fgag.com;a=blobdiff_plain;f=blackforestfire.mdwn;h=6623d37752a81f3617bdb3180d0e69b531f27836;hp=5c5d35ea6ea6c039d0223bb1861974366c7ba430;hb=5fef2212d7e10856fe013cbf18655b6da83b12fa;hpb=d6001643596d65ae7bdd8caf7bac563858373755
diff --git a/blackforestfire.mdwn b/blackforestfire.mdwn
index 5c5d35e..6623d37 100644
--- a/blackforestfire.mdwn
+++ b/blackforestfire.mdwn
@@ -14,6 +14,11 @@ survived. So we quickly decided to re-build on the same property, and hope
the new house will be ready by late summer 2014. In the meantime, we're
living in an apartment in nearby Colorado Springs.
+If you want to hear more about our experience, feel free to view the video
+of Bdale's
+[talk at Linux Conf Australia](https://www.youtube.com/watch?v=lJcnllq3VYY)
+about the fire and some of the lessons we learned.
+
###Helping###
For those of you who have asked how you can help us restore and rebuild,
@@ -48,6 +53,13 @@ were directly fighting the fire on and around our property:
### Journal ###
+* 2014 July 31
Hardwood floors are in, tile floors are in process, finish
+ electrical has started, trim material in the process of being stained.
+* 2014 June 10
Rough-in inspections for plumbing, electrical, HVAC, and
+ so forth all completed... on to insulation!
+* 2014.May 8
Exterior doors and windows in, roofing begun,
+ duct work underway.
+* 2014.April 26
Concrete slabs for basement and garage floor poured.
* 2014 April 9
Roof trusses installed.
* 2014 March 25
Framing started.
* 2014 March 14
Concrete poured for the foundation / basement walls.