@@ -14,6 +14,11 @@ survived. So we quickly decided to re-build on the same property, and hope
the new house will be ready by late summer 2014. In the meantime, we're
living in an apartment in nearby Colorado Springs.
+If you want to hear more about our experience, feel free to view the video
+of Bdale's
+[talk at Linux Conf Australia](https://www.youtube.com/watch?v=lJcnllq3VYY)
+about the fire and some of the lessons we learned.
+
###Helping###
For those of you who have asked how you can help us restore and rebuild,
@@ -48,6 +53,20 @@ were directly fighting the fire on and around our property:
### Journal ###
+* 2014 October 3
Finished cleaning up the apartment and associated garages,
+ and turned in those keys.
+* 2014 September 27
Began to move out of the apartment and in to our new
+ house! We're home!
+* 2014 September 25
Our builder passed his final inspection with regional
+ building! A list of final (mostly cosmetic) details to finish up,
+ then we can move in.
+* 2014 July 31
Hardwood floors are in, tile floors are in process, finish
+ electrical has started, trim material in the process of being stained.
+* 2014 June 10
Rough-in inspections for plumbing, electrical, HVAC, and
+ so forth all completed... on to insulation!
+* 2014.May 8
Exterior doors and windows in, roofing begun,
+ duct work underway.
+* 2014.April 26
Concrete slabs for basement and garage floor poured.
* 2014 April 9
Roof trusses installed.
* 2014 March 25
Framing started.
* 2014 March 14
Concrete poured for the foundation / basement walls.