### Journal ###
+* 2013 December 16
Got our "last" set of questions answered by our
+ contractor, and signed the contract for constuction of our new house.
+* 2013 December 10
Met with contractor to review cost estimates for our
+ revised plan. We're within budget now, so gave him the go-ahead to
+ write up a contract!
+* 2013 November 25
Met with contractor and architect to deliver our
+ proposed updates to the plan and discuss. We're actually happier
+ with the revised design, they both seem to like what we proposed,
+ and everyone is optimistic it will come in within budget.
+* 2013 November 18
Met with our contractor to discuss costs. Not too
+ surprisingly in hindsight, what we designed would cost more to build
+ than we are prepared to spend. Back to the drawing board, literally!
* 2013 November 2
Met with our contractor to provide information he needs
- to put cost estimates together for us.
+ to put cost estimates together for us in parallel with waiting for
+ structural engineering work to be completed.
* 2013 October 21
After several iterations, we now have floor plans and
elevations that accurately represent what we'd like to build.
* 2013 September 19
First draft of main floor plan received from the
@@ -64,7 +77,8 @@ were directly fighting the fire on and around our property:
* 2013 July 21
After a week spent interviewing contractors who might help us
build a new house, we made a decision! We'll be working with Doug
Strecker, dba Rampart
- Custom Homes.
+ Custom Homes. At his suggestion, we'll be using David Woody as
+ the architect tasked with turning our sketches into working plans.
* 2013 July 4
all web sites formerly hosted returned to normal
* 2013 July 3
gag.com web presence returns to normal