### Journal ###
+* 2014 September 27<br>Moved out of the apartment and in to our new house!
+ We're home! Lots still to do before life settles down, but we all
+ had smiles on this morning...
+* 2014 September 25<br>Our builder passed his final inspection with regional
+ building! A list of final (mostly cosmetic) details to finish up,
+ then we can move in.
+* 2014 July 31<br>Hardwood floors are in, tile floors are in process, finish
+ electrical has started, trim material in the process of being stained.
+* 2014 June 10<br>Rough-in inspections for plumbing, electrical, HVAC, and
+ so forth all completed... on to insulation!
+* 2014.May 8<br>Exterior doors and windows in, roofing begun,
+ duct work underway.
+* 2014.April 26<br>Concrete slabs for basement and garage floor poured.
* 2014 April 9<br>Roof trusses installed.
* 2014 March 25<br>Framing started.
* 2014 March 14<br>Concrete poured for the foundation / basement walls.